O&Ms: The Problem With Procuring Late

On a typical construction project, the main contractor has between 30 – 40 subcontractors to procure and manage. Procurement is largely driven by the construction plan which means an O&M provider is often appointed late in the project.

This creates a problem as the time it takes to collate and review 30 – 40 O&M submissions should not be underestimated. Condensing this activity into a few weeks or months before PC gives the contractor, supply chain and O&M provider little time to manage the task properly.

Ultimately, this can lead to project delays or the risk of incomplete O&Ms at PC.

Issues With Late Engagement
  • Added cost for O&Ms not previously budgeted for
  • Trades already left site and fully paid
  • No standardisation across O&M submissions
  • Increased pressure on site teams close to PC
  • Risk of missing or incomplete O&M submissions
  • Unhappy end client

 

“Through early integration and involvement with the project team, Createmaster understood clearly both the Client aspirations and the scope of the sub-contract packages allowing them to manage the whole process. Early involvement with the project team facilitated the development of a solution to integrate the O&M database with the 3D model and meet Client aspirations”.
Project Manager – Sir Robert McAlpine

 

Why Procuring O&Ms Early Makes Sense
Procuring the O&M package early in the project, makes everybody’s life easier, as the dedicated O&M provider can manage the supply chain in line with the construction plan.

O&M templates can be included in trade contracts to ensure a standardised format is followed. Managing trades as they start on site gives enough time to conduct a thorough review process and makes sure a complete and accurate set of O&Ms is delivered at PC.

The end result is less stress for the main contractor at handover and a happy client with all the information needed to run and maintain their building safely and effectively.

Benefits of Early Engagement
  • Cost certainty – a realistic budget for O&Ms in the cost plan
  • O&M templates in contract documents
  • Free up valuable site resource
  • Trades managed as and when they start on site
  • Plenty of time to conduct a thorough O&M review
  • Smooth, pain free handover at PC
  • Happy client with a complete and accurate as built record
To summarise:
At Createmaster, we avoid working on projects with less than three months until practical completion. Why? Because it is a near impossible task to manage a full supply chain in such a condensed time frame.

Appoint an O&M provider at the start of the project and gain the full benefits of early engagement – a fully managed process delivering a complete and accurate as built record at PC.

LEARN MORE ABOUT BEST PRACTICE

Related Articles

Want to get started with Createmaster?

BOOK A DEMO

Join the Createmaster mailing list

You may unsubscribe from these communications at any time. For information on how to unsubscribe, as well as our privacy practices, please review our Privacy Policy.